#16 retaining wall project


The maintenance team as begun installing sod along the pond edge and around to the bunker left of the green.  Although staples are being used to help keep the sod in place, please be careful when stepping on these slopes because the sod is unable to root in during dormancy.  The rest of the project is on hold for a few weeks until the bridge piers can be installed.  Then the remaining sod and cart paths can be installed.