Day two of the bunker renovation has
been very productive.  Since finishing removal of all old sand yesterday, the old drainage material has been removed and additional drainage trenches were dug out.  Our assistant superintendent, Michael Liebe, was in the mini excavator knocking down the old bunker edge on the west half that is to be converted to a sod basin.  Tomorrow we will finish the grading the soil and get the area ready for sod while simultaneously installing the new drain pipe and gravel in the right side of the bunker.  If all goes well, we should be ready for sod and new sand by the end of the week.