Pond dam before project. |
Once dirt and limestone rocks were removed, the contractor chiseled into bedrock to prepare for weir footing. |
The footing was chiseled 2' into the bedrock, then a rebar frame is installed. |
Once the rebar was installed, concrete for the footing was poured. |
The footing cured for almost a week, then the wall forms were installed and concrete was poured. |
After 3 days, the formed were removed and we had "a wall in a hole" as one of our members put it. At this point it's still hard to visualize what the finished product will be. |
With all concrete work completed, the contractor got busy installing the clay on either side of the wall. Starting to look like something now. |
All of the limestone that was discovered early in the project was reused to stabilize the pond banks and give the downstream side more character |
Finshed the project just in time to get a big rain and fill the pond behind the weir. Couldn't be happier with how it turned out. |
This is actually the kind of information I have been trying to find. Thank you for writing this information.
ReplyDeleteJohn Odom