The place to get a behind-the-scenes look at grounds maintenance at Bailey Ranch Golf Club
Monday, March 7, 2011
#16 Bridge Project
Since the bridge was lifted into position last week, the turf maintenance team has been working very hard pouring concrete for the paths leading up to, and away from, the bridge on #16 green. Wooden forms were installed and steel was used to reinforce the cart path.
Now that all the concrete has been poured, the next step in the process is the installation of the curbing. We will begin drilling rods into the edge of the path and installing our forms tomorrow. The plan is to pour the concrete tomorrow afternoon. Once everything is dry we will begin grading the soil. alongside the path and install sod.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment