Thursday, January 27, 2011

#16 Bridge project



Over the last few days, golf maintenance staff has been coordinating with the Public Works department in constructing the abutments for the bridge behind #16 green.  First the holes for the piers were dug using an auger.  Second, the wood forms were built with steel anchors and crossbars for added strength.  Yesterday the concrete was poured and covered.  The concrete will need to cure for approximately 28 days.  Once the concrete has cured, the bridge can be installed and cart paths can be poured.